Substations and switchrooms should be assessed for environmental risks (flooding, drainage overflow, ventilation), not sited under bulk water or wet services, located per HTM 05-02 fire adjacencies, built from fire-resisting materials to Approved Document B, robust enough to contain an internal electrical explosion (external units with pressure relief), protected against water ingress, bunded where fluid-filled transformers are used, and finished to limit dust. Outward-opening doors should be large enough to replace equipment. External equipment should be kept clear of live vegetation by at least 3 m.