Maintenance programmes should include an annual longer test proving engine condition up to 110% of full load for not less than 3 hours and ideally 4. During it the safety chain should be tested: operate the overspeed governor, simulate over-temperatures to check alarms and action, and force the fuel rack off to check automatic shutdown; these tests should not be done when only one generator is running (island or parallel). A safety document or sanction for test may be needed for any secondary supply test.