NFPA 111-2025 Standard on Stored Electrical Energy Emergency and Standby Power Systems
Chapter 7: Installation and environmental considerations – NFPA 111-2025 Standard on Stored Electrical Energy Emergency and Standby Power Systems

NFPA 111-2025 Standard on Stored Electrical Energy Emergency and Standby Power Systems 7.6.2.3: 7.6.2.3 System load test

After the recharge period a system load test is run on the site load, augmented by a load bank sized to the ECE rating if needed, for the full class duration, following the same steps as the initial test; unity power factor is accepted for an ac SEPSS if rated power factor results are within the maker's stated design parameters.

Maintained by Gerard Blokdyk

What else in your programme already covers this

This control maps to 2 controls across 2 other frameworks. If you already hold one of them, the evidence you collected for it is the starting point here rather than new work.

  • 7.13.4 7.13.4 Conduct of the on-site acceptance test
  • 16.13-16.16 UPS commissioning: changeover, waveform, harmonics, true battery autonomy and alarms

Every mapping shown was judged rather than inferred from wording similarity, and the ones that failed review are published too. See the coverage reports and what was rejected.

Other controls in Chapter 7: Installation and environmental considerations – NFPA 111-2025 Standard on Stored Electrical Energy Emergency and Standby Power Systems

Query this from an agent

The graph holds this control, the 2 it maps to, and the evidence behind each claim, over MCP and REST.