The UPS should give a no-break supply rated for the load for the required endurance, with battery ampere-hour capacity verified under load. Commissioning should prove changeover within limits or no-break, output waveform and THD within specification, and true autonomy at full load on a load bank. UPS room environmental conditions should be commissioned to protect battery life, and all local and remote indications and alarms should be demonstrated and recorded.