Level 1 starting and control batteries are inspected weekly and Level 2 monthly, kept fully to the maker's recommendations including electrolyte level and voltage. Batteries with access to the electrolyte are tested monthly with specific gravity recorded, or by an alternative method; batteries without electrolyte access are tested monthly by conductance, ohmic, carbon pile load or cranking voltage drop testing. Defective batteries are replaced as soon as found.