Schematics showing all points of isolation and interconnection between PES, generators and tertiary supplies should be provided at all HV and LV panel locations. As-installed drawings should at least include: whole-site HV layout and schematic; HV switching and transformer schedule with relay settings; principal earthing drawing with measured electrode resistances; LV main distribution layouts and schematics per substation and switchroom with cable sizes, device settings and fault levels; final distribution schematics per board; 1:20 general arrangements of substations, generator houses, CHP rooms, switchrooms and risers; system and control wiring; and a site Medical Location classification drawing.