NHS England HTM 06-01 Electrical Services Supply and Distribution (2017 Edition)
Chapter 16: Validation, commissioning and records – NHS England HTM 06-01 Electrical Services Supply and Distribution (2017 Edition)

NHS England HTM 06-01 Electrical Services Supply and Distribution (2017 Edition) 16.17-16.23: Medical IT commissioning and validation including changeover times

Medical IT systems should be commissioned to BS 7671 Section 710 and the maker's recommendations: correct and labelled protective devices; local and remote alarms demonstrated; circuit insulation resistances measured and compared with the IMD reading, with the IMD alarm proven by reducing insulation; transformer leakage current with secondary open below 0.5 mA; changeover at the common coupling point proven no-break, within 0.5 s or within 15 s as intended; supplementary bonding measured and recorded including extraneous metalwork and outlets relative to the EBB.

Maintained by Gerard Blokdyk

Other controls in Chapter 16: Validation, commissioning and records – NHS England HTM 06-01 Electrical Services Supply and Distribution (2017 Edition)

Query this from an agent

The graph holds this control, the 0 it maps to, and the evidence behind each claim, over MCP and REST.