NFPA 111-2025 Standard on Stored Electrical Energy Emergency and Standby Power Systems 8.4.4: 8.4.4 Annual load test

Once a year the SEPSS is load tested either at its full rated load for 60 percent of its class duration or at 60 percent of rated load for the whole class duration.

Maintained by Gerard Blokdyk

What else in your programme already covers this

This control maps to 2 controls across 2 other frameworks. If you already hold one of them, the evidence you collected for it is the starting point here rather than new work.

  • 8.4.2.3 8.4.2.3 Annual supplemental load test
  • 17.102-17.105 UPS functional tests at least six-monthly and full service tests

Every mapping shown was judged rather than inferred from wording similarity, and the ones that failed review are published too. See the coverage reports and what was rejected.

Other controls in Chapter 8: Routine maintenance and operational testing – NFPA 111-2025 Standard on Stored Electrical Energy Emergency and Standby Power Systems

Query this from an agent

The graph holds this control, the 2 it maps to, and the evidence behind each claim, over MCP and REST.