NFPA 110-2025 Standard for Emergency and Standby Power Systems 8.4.6: 8.4.6 Monthly transfer switch operation

Transfer switches are operated monthly by electrically moving them from the primary to the alternate position and back. Where several ATSs serve a system, the switch used to start the monthly test is rotated so every switch is proven over time.

Maintained by Gerard Blokdyk

What else in your programme already covers this

This control maps to 1 controls across 1 other frameworks. If you already hold one of them, the evidence you collected for it is the starting point here rather than new work.

  • 17.81-17.83 Monthly on-load generator test of at least one hour including changeover

Every mapping shown was judged rather than inferred from wording similarity, and the ones that failed review are published too. See the coverage reports and what was rejected.

Other controls in Chapter 8: Routine maintenance and operational testing – NFPA 110-2025 Standard for Emergency and Standby Power Systems

Query this from an agent

The graph holds this control, the 1 it maps to, and the evidence behind each claim, over MCP and REST.