Victoria Occupational Health and Safety Regulations 2017
Part 6.1: Licences – Victoria Occupational Health and Safety Regulations 2017

Victoria Occupational Health and Safety Regulations 2017 r472: r 472 Pay the processing fee before a major hazard facility licence is granted

The Authority cannot grant a major hazard facility licence until the applicant has paid 9.3 fee units per hour spent processing the application, up to a ceiling of 6570.9 fee units. Processing includes checking the safety case and accompanying material for completeness, obtaining further information, verifying the material by examining the documents and visiting the site, deciding the merits and completing the administrative steps.

Maintained by Gerard Blokdyk

Other controls in Part 6.1: Licences – Victoria Occupational Health and Safety Regulations 2017

Query this from an agent

The graph holds this control, the 0 it maps to, and the evidence behind each claim, over MCP and REST.