Every task team shall draw up a TIDP and keep it up to date for the whole appointment. It considers the milestones, what the detailed matrix makes the team responsible for, the requirements of the lead appointed party, the shared resources available, and the time needed to produce, coordinate, review and approve information. For each container the TIDP shall give the container's name and title, any dependencies or predecessors, the level of information need, how long production is expected to take, the responsible author and the delivery milestones.