ECSS-E-ST-10C System Engineering General Requirements (2009 edition) 6.7: Phase D: complete qualification and acceptance and prepare for operations

What does 6.7 require?

In phase D the supplier's system engineering function finalises the development of the system through qualification and acceptance, finalises the preparation for operations and utilisation, supports the Qualification Review and the Acceptance Review, and sees that their actions are implemented.