The lead appointed party combines the task teams' TIDPs into the delivery team's MIDP, notifies each task team of changes its TIDP needs, and records new or revised risks in the team's risk register, keeping the appointing party informed where required. It considers the responsibilities in the detailed responsibility matrix; predecessors and dependencies across task teams and the TIDP changes these cause; how long it needs to review and authorize deliveries; and how long the appointing party needs to review and accept them.