Each task team prepares a TIDP and keeps it current for the whole appointment, considering the asset management delivery milestones, what the detailed responsibility matrix assigns to it, the EIR (ISO 19650-3) issued by the lead appointed party, the reference information and shared resources available to the team, and how long it needs to produce its information. For every container the TIDP gives a unique ID and title, any dependencies or predecessors, the level of information need, how long production is expected to take, the responsible information author, and the delivery milestones.