Starting from the high-level matrix, the lead appointed party shall draw up a detailed responsibility matrix showing which information is produced, when and to whom it is passed, and which task team produces it. It considers the milestones, the high-level matrix, the production methods and procedures, which parts of the container breakdown structure each task team holds, and how production tasks depend on one another.