ISO 10006:2017
Clause 6: Resource management in projects – ISO 10006:2017

ISO 10006:2017 6.1.1: General: resource-related processes

What does 6.1.1 require?

Resource processes exist to plan and control resources and help bring resource problems to light early. Resources include, for example, people, facilities, equipment, finance, information, materials, software and services. The processes are resource planning (6.1.2) and resource control (6.1.3). This sub-clause deals with the quantitative side of managing people; training and other aspects are in 6.2.

Maintained by Gerard Blokdyk

Other controls in Clause 6: Resource management in projects – ISO 10006:2017