ISO 10006:2003 7.5.4: Cost control

What does 7.5.4 require?

Before money is spent, a cost control system and its processes should be set up, documented and made known to everyone who authorizes work or spending. The timing of reviews and how often data are collected and forecasts made should be fixed. The project organization should check that the work still to do can be finished within the budget still available; departures beyond set limits should be analysed and acted on; cost trends should be analysed using methods such as earned value analysis, with the plan for the remaining work reviewed for uncertainty; the root causes of variances, good and bad, should be found and used for continual improvement, with adverse variances kept from harming the objectives; decisions should rest on facts and take account of their effect on other processes; cost changes should be approved and authorized before any spending; any revised budget forecast should be aligned with other processes; resource control should receive the information needed to release funds on time; and cost reviews should be held regularly as planned, taking account of other financial reviews, external ones included.

Maintained by Gerard Blokdyk

Other controls in Clause 7.4 and 7.5: Time-related and cost-related processes – ISO 10006:2003

Query this from an agent

The graph holds this control, the 0 it maps to, and the evidence behind each claim, over MCP and REST.