ISO 10006:2003 7.4.1: General: time-related processes

What does 7.4.1 require?

The time-related processes determine dependencies and durations of activities and ensure timely completion of the project; they are planning of activity dependencies (7.4.2), estimation of duration (7.4.3), schedule development (7.4.4) and schedule control (7.4.5).