ISO 10006:2003 7.4.2: Planning of activity dependencies

What does 7.4.2 require?

The dependencies between project activities should be identified and checked to make sure they are consistent, and any need to alter the data coming from activity identification should be justified and documented. Where possible, standard or tried and tested network diagrams should be used so that earlier experience is put to use, after checking that they suit the project.