The people responsible for the activities should produce the duration estimates. Estimates based on past experience should be checked for accuracy and relevance, inputs should be recorded so they can be traced back to their origin, and the related resource estimates should be gathered at the same time to feed resource planning (6.1.2). Where an estimate is highly uncertain, the risks should be assessed, documented and reduced, with an allowance for the risk that remains included in the estimate, and, where this is needed or appropriate, the customer, or any other interested party, should take part.