Input data should be identified and checked against the conditions of the project. The critical path should be worked out with activities of long duration or long lead time in mind, and the critical path must be stated explicitly. Standard schedule formats should be used to suit the needs of different users. Duration estimates and dependencies should be checked against each other and any inconsistency settled before schedules go out. Critical and near-critical activities should be identified, as should key events or milestones that need particular inputs or decisions or that deliver major outputs. Progress evaluations should appear in the schedule. Where needed, interested parties, the customer among them, should take part and be kept informed; outside inputs such as items that depend on the customer should be analysed and built in; and suitable schedules should be given to the customer and interested parties for information or for approval.