EPA Risk Management Program (40 CFR Part 68) 68.77: § 68.77 Pre-startup review

A pre-startup safety review is required for new stationary sources and for modifications significant enough to change the process safety information, confirming before regulated substances are introduced that construction and equipment match design specifications; safety, operating, maintenance and emergency procedures are in place and adequate; for new sources a PHA has been performed and its recommendations resolved or implemented, and for modified sources the management of change requirements are met; and training of each operating employee is complete.