EPA Risk Management Program (40 CFR Part 68)
Program 3 Prevention (PSM-equivalent)

EPA Risk Management Program (40 CFR Part 68) 68.67: Process Hazard Analysis with 5-year revalidation

Program 3 processes must conduct PHA using HAZOP, What-If, FMEA, Fault Tree, or equivalent methodology by a team including operations expertise. PHA must address process hazards, prior incidents, engineering and administrative controls, siting, human factors, natural hazards, and safer technology alternatives. PHA must be revalidated every five years with records retained for the process lifetime.