ISO 10006:2003 7.3.5: Control of activities

What does 7.3.5 require?

Activities should be performed and controlled in line with the project management plan, which includes managing how activities interact so that misunderstanding and conflict are kept to a minimum, with particular care for processes that use new technology. Activities should be reviewed and assessed for possible deficiencies and chances to improve, as often as the project's complexity warrants, and the results should be used in progress evaluations to judge process outputs and to plan the work that remains, with the revised plan for that work documented.