ISO 10006:2003
Clause 7.2 and 7.3: Interdependent and scope-related processes – ISO 10006:2003

ISO 10006:2003 7.2.1: General: interdependency-related processes

What does 7.2.1 require?

A project is a system of planned processes that depend on each other, so that action in one usually affects the others. The project manager is responsible for managing these planned interdependencies as a whole, and the project organization should manage good communication between the various groups of people involved and give them clearly assigned responsibilities. The interdependency processes are: starting the project and developing its management plan (7.2.2), managing interactions (7.2.3), managing change (7.2.4), and closing processes and the project (7.2.5).

Maintained by Gerard Blokdyk