Change management covers identifying, evaluating, authorizing, documenting, implementing and controlling changes. Before authorizing a change, its purpose, extent and effects should be analysed, and any change affecting the objectives needs to be agreed by the customer and by other interested parties. Change management should control changes to the scope, the objectives and the project management plan; coordinate changes across linked processes and settle any conflicts; provide processes for recording changes; connect with improvement (8.3); and consider how changes affect people (6.2.4). The effects of a change should be identified as early as possible and their root causes analysed and used for solutions and for improving processes. A justified change request should be submitted under the plan's processes before the change is made. Configuration management of what the project produces, whether deliverable or not, forms part of change management (ISO 10007).