NASA NPR 7123.1D Systems Engineering Processes and Requirements SE-64: Create and maintain review trends including closure of review action documentation

What does SE-64 require?

The technical team ensures that review trends are built up and kept current, including the closure of review action documentation such as review item discrepancies, requests for action and action items as the project establishes them.