The plan should be checked for adequacy and effectiveness and given formal approval by an authorized individual, or by a group drawn from the relevant functions. Under a contract it may go to the customer for review and acceptance, before or after award; after award it should be looked at again and, where appropriate, updated for any requirement changes since the pre-contract discussions, and where a project or contract proceeds in stages a plan may be expected for each stage before that stage begins.