Having decided to prepare a quality plan, the organization should work out what feeds into it: what the specific case requires; what the plan itself must meet, including customer, statutory, regulatory and industry specifications; the organization's QMS requirements; risk assessments on the case; what resources are needed and whether they are available; what the people doing the work, and other interested parties who will rely on the plan, need; other quality plans that are relevant; and other plans, for example for the project, security, information management, the environment, or health and safety.