IEC 61508:2010 - Functional Safety of E/E/PE Safety-related Systems 1-7.9.2: Part 1, 7.9.2 Overall installation and commissioning planning: requirements

An installation plan specifies the schedule, who is responsible for each part, the procedures, the integration sequence of elements, criteria for declaring systems ready for installation and installation complete, and how failures and incompatibilities are resolved. A commissioning plan specifies its schedule, responsibilities, procedures, and its links to installation steps and to validation. Both are documented.