ISO/IEC/IEEE 12207:2017
Clause 6.3: Technical management processes – ISO/IEC/IEEE 12207:2017

ISO/IEC/IEEE 12207:2017 6.3.1: Project Planning process: produce and coordinate workable plans and activate them

What does 6.3.1 require?

The project defines its objectives and plans, including scope, process outputs, tasks, deliverables, schedules with achievement criteria and the resources needed; defines roles, responsibilities, accountabilities and authorities; formally requests and obtains commitment of the resources and services needed; and activates the plans, revising them throughout the project. Activities: define the project, plan project and technical management, activate the project.

Maintained by Gerard Blokdyk

Other controls in Clause 6.3: Technical management processes – ISO/IEC/IEEE 12207:2017