ISO 10006:2017 7.4.2: Planning of activity dependencies

What does 7.4.2 require?

Dependencies among project activities should be identified and checked for consistency, and any need to alter the data coming from activity identification should be justified and documented. Wherever possible, standard or proven network diagrams should be reused while developing the project plan to benefit from past experience, after checking that they suit this project.