Clause 7.8: Procurement processes – ISO 10006:2003

ISO 10006:2003 7.8.6: Contract control

What does 7.8.6 require?

Contract control starts when the contract is placed, or when an agreement in principle such as a letter of intent is reached, and relies on a system making sure the contract's conditions, due dates and required documents and records included, are fulfilled. It should set up suitable contractual relationships and bring what they deliver into the management of the project as a whole; track supplier performance against the contract's conditions, feeding results back and agreeing actions; and, before closing the contract, confirm every condition has been met and that feedback on the supplier's performance has been gathered to update the approved supplier register.