A purchasing plan should list and schedule the products or services to be bought, together with their specification, timing and cost requirements. Every product coming into the project should be subject to equal purchasing control, whether it comes from external suppliers or from inside the originating organization; internal supply goes through internal acquisition processes in which some controls can be lighter. Purchases should be planned in a way that leaves the project organization able to manage its interfaces and interactions with suppliers; enough time should be allowed; past supplier performance should be used to anticipate problems such as long lead times; and progress in purchasing should be reviewed regularly against the plan, with action taken and the results fed into progress evaluations.