Ghana Cybersecurity Act 36.3: Section 36(3): tell the Authority of a change in legal ownership within seven days

What does 36.3 require?

Where the legal ownership of a registered critical information infrastructure changes, its owner must inform the Authority within seven days after the change. Failure carries the Second Schedule administrative penalty of 500 to 10,000 penalty units (a penalty unit is GHS 12, the value the Authority's August 2026 sanctions applied).