Planning covers the additional considerations the project triggers: previously developed software, tool qualification, alternative methods such as product service history, user-modifiable and deactivated code, and any technology supplement used. Table A-1 objective 4, described in 4.1.d; applies at levels A, B, C, D, no independence required; activities 4.2.f, 4.2.h, 4.2.i, 4.2.j, 4.2.k; outputs PSAC, SDP, SVP, SCM Plan, SQA Plan. The revision added a planning activity (4.2.k) for this objective, which previously had none, and requires deactivated code and the means preventing its inadvertent activation to be identified in the plans.