Back to Frameworks

NSW Gateway Review System

Australia (New South Wales)
vDigital NSW DSSA guideline and workbook set version 3 (April 2026); Infrastructure NSW Gate 0 workbook version 7 (March 2026), Gate 5 and Health Check in Delivery workbooks version 3 (June 2021)
8 domains
449 controls

The NSW Government's gateway review system: what delivery agencies are expected to show and review teams probe at Gate 0, Gate 2, Gate 3, Gate 5, Gate 6, the Health Checks and the Rapid Assurance Review for digital projects, with the Infrastructure NSW key focus areas at Gate 0, Gate 5 and the delivery Health Check, and the steps for initiating and conducting a review.

Verified

NSW Gateway Review System is a compliance framework from Australia (New South Wales) with 8 domains and 449 controls. The largest domains are Health Check reviews – NSW Gateway Review System (165 controls), Gate 3: Pre-execution – NSW Gateway Review System (70 controls), Gate 5: Pre-commissioning and readiness for service – NSW Gateway Review System (67 controls). Every control below carries what it requires and what an assessor expects to see.

Maintained by Gerard Blokdyk

Framework summaries on this platform are interpretations grounded in the published source, for educational and compliance planning purposes. They do not reproduce or replace the official standards. Refer to the authoritative source for the definitive text. Framework names and trademarks belong to their respective organisations.

Framework Domains (8)

Gate 0: Go/No-go (project initiation) – NSW Gateway Review System

17 controls
Controls in the Gate 0: Go/No-go (project initiation) – NSW Gateway Review System domain of NSW Gateway Review System: 17 controls
CodeTitle
nsw-gateway-review-system::DSSA-G0-3.2Registering and initiating a Gate 0 review
nsw-gateway-review-system::DSSA-G0-3.3Agency ownership of the gateway review
nsw-gateway-review-system::DSSA-G0-3.3.1Mandatory documents for the Gate 0 review
nsw-gateway-review-system::DSSA-G0-3.3.2Optional supplementary project information
nsw-gateway-review-system::DSSA-G0-4.1Running the Gate 0 review
nsw-gateway-review-system::DSSA-G0-4.2Committee interviews and overall rating
nsw-gateway-review-system::DSSA-G0-4.7Assessing objectives and scoring focus questions
nsw-gateway-review-system::DSSA-G0-7.2.1Strategic need and early risk identification
nsw-gateway-review-system::DSSA-G0-7.2.2Urgency, end user need and benefits
nsw-gateway-review-system::INSW-G0-AFFORDABILITYCost range and funding for next stages
nsw-gateway-review-system::INSW-G0-ALTERNATIVESConsideration of non-asset and existing asset options
nsw-gateway-review-system::INSW-G0-GOVERNMENT-PRIORITYAlignment with a stated government priority
nsw-gateway-review-system::INSW-G0-INITIATING-THE-REVIEWRegistering and initiating before development
nsw-gateway-review-system::INSW-G0-MANDATORY-DOCUMENTSGate 0: documents and approvals that are mandatory
nsw-gateway-review-system::INSW-G0-PLANNING-INTERFACESPlanning pathway and project dependencies
nsw-gateway-review-system::INSW-G0-STRATEGIC-ASSET-MANAGEMENTPriority in approved asset planning
nsw-gateway-review-system::INSW-G0-URGENCYCriticality and urgency of the service need

Gate 2: Business case – NSW Gateway Review System

66 controls
Controls in the Gate 2: Business case – NSW Gateway Review System domain of NSW Gateway Review System: 66 controls
CodeTitle
nsw-gateway-review-system::DSSA-G2-3.2Initiating a Gate 2 review
nsw-gateway-review-system::DSSA-G2-3.3.1Mandatory documents for the review
nsw-gateway-review-system::DSSA-G2-3.3.2Required project information
nsw-gateway-review-system::DSSA-G2-4.1Gate 2 review approach
nsw-gateway-review-system::DSSA-G2-4.2How the Gate 2 review is conducted
nsw-gateway-review-system::DSSA-G2-4.7Coverage of review objectives
nsw-gateway-review-system::DSSA-G2-7.2.1Delivery options assessed against needs and priorities
nsw-gateway-review-system::DSSA-G2-7.2.10Time, cost and resourcing implications assessed
nsw-gateway-review-system::DSSA-G2-7.2.11Acceptance that early work may be discarded
nsw-gateway-review-system::DSSA-G2-7.2.12Capacity to run parallel developments
nsw-gateway-review-system::DSSA-G2-7.2.13Development aligned with change portfolio
nsw-gateway-review-system::DSSA-G2-7.2.2Shared understanding of business needs
nsw-gateway-review-system::DSSA-G2-7.2.3Requirement specification reflects agreed outcomes
nsw-gateway-review-system::DSSA-G2-7.2.4Alignment with whole-of-government ICT direction
nsw-gateway-review-system::DSSA-G2-7.2.5Delivery influences identified and handled
nsw-gateway-review-system::DSSA-G2-7.2.6Strategy supports communication and cooperation
nsw-gateway-review-system::DSSA-G2-7.2.7Delivery methodology chosen and agreed
nsw-gateway-review-system::DSSA-G2-7.2.8Culture ready for the chosen method
nsw-gateway-review-system::DSSA-G2-7.2.9Stakeholders understand strategy and commitments
nsw-gateway-review-system::DSSA-G2-7.3.1Business case aligned with Treasury guidance
nsw-gateway-review-system::DSSA-G2-7.3.10Business change risks owned and planned
nsw-gateway-review-system::DSSA-G2-7.3.11ICT security requirements identified early
nsw-gateway-review-system::DSSA-G2-7.3.12Stakeholder support and delivery commitment
nsw-gateway-review-system::DSSA-G2-7.3.13Benefits agreed and a plan to realise them
nsw-gateway-review-system::DSSA-G2-7.3.14Process for managing organisational change
nsw-gateway-review-system::DSSA-G2-7.3.15Affected business units shape the change plan
nsw-gateway-review-system::DSSA-G2-7.3.16Change identified, assessed and communicated
nsw-gateway-review-system::DSSA-G2-7.3.17Formal ICT governance endorsed by the Sponsor
nsw-gateway-review-system::DSSA-G2-7.3.18Roles, responsibilities and delegations defined
nsw-gateway-review-system::DSSA-G2-7.3.19Staff training needs planned
nsw-gateway-review-system::DSSA-G2-7.3.2Business case validity and strategic fit
nsw-gateway-review-system::DSSA-G2-7.3.20Change management controls operating
nsw-gateway-review-system::DSSA-G2-7.3.21Business users empowered to effect change
nsw-gateway-review-system::DSSA-G2-7.3.22Progress tracking and corrective action
nsw-gateway-review-system::DSSA-G2-7.3.23Business case supported by documentation
nsw-gateway-review-system::DSSA-G2-7.3.24Project Sponsor has capacity to lead
nsw-gateway-review-system::DSSA-G2-7.3.3Preferred option remains the right one
nsw-gateway-review-system::DSSA-G2-7.3.4Whole-life value for money demonstrated
nsw-gateway-review-system::DSSA-G2-7.3.5Whole-life funding affordable and supported
nsw-gateway-review-system::DSSA-G2-7.3.6Contingency sized to project complexity
nsw-gateway-review-system::DSSA-G2-7.3.7Cyber security protection costs included
nsw-gateway-review-system::DSSA-G2-7.3.8Realistic view of ability to succeed
nsw-gateway-review-system::DSSA-G2-7.3.9Total project scope clearly defined
nsw-gateway-review-system::DSSA-G2-7.4.1Major risks and issues identified and costed
nsw-gateway-review-system::DSSA-G2-7.4.2Risk management plans and ownership
nsw-gateway-review-system::DSSA-G2-7.4.3Resolution of issues and risk actions
nsw-gateway-review-system::DSSA-G2-7.4.4External statutory and communication issues
nsw-gateway-review-system::DSSA-G2-7.4.5Staff wellbeing and burnout prevention
nsw-gateway-review-system::DSSA-G2-7.4.6AI use and risk assessment
nsw-gateway-review-system::DSSA-G2-7.4.7AI risk mitigation measures
nsw-gateway-review-system::DSSA-G2-7.5.1Project control of cost and schedule
nsw-gateway-review-system::DSSA-G2-7.5.2Causes of cost and time deviation
nsw-gateway-review-system::DSSA-G2-7.5.3Actions to stop deviation recurring
nsw-gateway-review-system::DSSA-G2-7.5.4Assumptions from Gate 2 still unverified
nsw-gateway-review-system::DSSA-G2-7.5.5Budget fit to delivery burn rate
nsw-gateway-review-system::DSSA-G2-7.6.1Realism of the remaining stage plan
nsw-gateway-review-system::DSSA-G2-7.6.10External dependencies into development work
nsw-gateway-review-system::DSSA-G2-7.6.11Status reporting set up for next phase
nsw-gateway-review-system::DSSA-G2-7.6.2Reasonable timescales for the project
nsw-gateway-review-system::DSSA-G2-7.6.3Time to fix faults and slippage monitoring
nsw-gateway-review-system::DSSA-G2-7.6.4Activities defined and resourced for next phase
nsw-gateway-review-system::DSSA-G2-7.6.5Team skills, experience and capacity
nsw-gateway-review-system::DSSA-G2-7.6.6Resources to hold momentum in mixed teams
nsw-gateway-review-system::DSSA-G2-7.6.7Procurement procedure and strategy proposals
nsw-gateway-review-system::DSSA-G2-7.6.8End user readiness for transition
nsw-gateway-review-system::DSSA-G2-7.6.9Data transfer, integration and exit planning

Gate 3: Pre-execution – NSW Gateway Review System

70 controls
Controls in the Gate 3: Pre-execution – NSW Gateway Review System domain of NSW Gateway Review System: 70 controls
CodeTitle
nsw-gateway-review-system::DSSA-G3-3.2Initiating a Gate 3 review
nsw-gateway-review-system::DSSA-G3-3.3.1Mandatory review documents
nsw-gateway-review-system::DSSA-G3-3.3.2Existing project information
nsw-gateway-review-system::DSSA-G3-4.1How the review is approached
nsw-gateway-review-system::DSSA-G3-4.2Conduct of the review
nsw-gateway-review-system::DSSA-G3-4.7Coverage of review objectives
nsw-gateway-review-system::DSSA-G3-7.2.1Delivery options weighed against needs and priorities
nsw-gateway-review-system::DSSA-G3-7.2.10Strategy supports communication and cooperation
nsw-gateway-review-system::DSSA-G3-7.2.11Supplier knowledge for likely success
nsw-gateway-review-system::DSSA-G3-7.2.12Contract management strategy sound
nsw-gateway-review-system::DSSA-G3-7.2.13Contracts conform to NSW procurement rules
nsw-gateway-review-system::DSSA-G3-7.2.14Evaluation strategy is accepted and compliant
nsw-gateway-review-system::DSSA-G3-7.2.15Alignment with whole of government ICT policy
nsw-gateway-review-system::DSSA-G3-7.2.16Agency culture ready for delivery
nsw-gateway-review-system::DSSA-G3-7.2.17Stakeholders grasp method and commitments
nsw-gateway-review-system::DSSA-G3-7.2.18Time, cost and resource effects considered
nsw-gateway-review-system::DSSA-G3-7.2.19Accepting that work may be discarded
nsw-gateway-review-system::DSSA-G3-7.2.2Delivery approach and method agreed with stakeholders
nsw-gateway-review-system::DSSA-G3-7.2.20Capacity for parallel developments
nsw-gateway-review-system::DSSA-G3-7.2.3Shared understanding of business needs
nsw-gateway-review-system::DSSA-G3-7.2.4Specification mirrors agreed outputs
nsw-gateway-review-system::DSSA-G3-7.2.5Procurement options and supply sources assessed
nsw-gateway-review-system::DSSA-G3-7.2.6Market appeal of the project
nsw-gateway-review-system::DSSA-G3-7.2.7Procurement procedure tested
nsw-gateway-review-system::DSSA-G3-7.2.8Outline delivery strategy set out
nsw-gateway-review-system::DSSA-G3-7.2.9Factors that shape the delivery strategy are handled
nsw-gateway-review-system::DSSA-G3-7.3.1Business case shows need and strategic fit
nsw-gateway-review-system::DSSA-G3-7.3.10Business change risks and issues understood
nsw-gateway-review-system::DSSA-G3-7.3.11Stakeholder support and agency commitment
nsw-gateway-review-system::DSSA-G3-7.3.12Benefits agreed and realisation planned
nsw-gateway-review-system::DSSA-G3-7.3.13Business units involved in change planning
nsw-gateway-review-system::DSSA-G3-7.3.14Change across areas is identified and managed
nsw-gateway-review-system::DSSA-G3-7.3.15Roles, delegations and authority defined
nsw-gateway-review-system::DSSA-G3-7.3.16Training for delivery and front line staff
nsw-gateway-review-system::DSSA-G3-7.3.17Benefit changes affecting project value
nsw-gateway-review-system::DSSA-G3-7.3.18Ongoing strategy for planning benefits
nsw-gateway-review-system::DSSA-G3-7.3.19Resources to keep momentum and fill gaps
nsw-gateway-review-system::DSSA-G3-7.3.2Fit within the wider change portfolio
nsw-gateway-review-system::DSSA-G3-7.3.20Business as usual survives staff moves
nsw-gateway-review-system::DSSA-G3-7.3.21Governance for progress and alignment
nsw-gateway-review-system::DSSA-G3-7.3.22Business change processes in place
nsw-gateway-review-system::DSSA-G3-7.3.23Tracking, reporting and correcting progress
nsw-gateway-review-system::DSSA-G3-7.3.3Preferred option still justified
nsw-gateway-review-system::DSSA-G3-7.3.4ICT security requirements identified
nsw-gateway-review-system::DSSA-G3-7.3.5Whole life value for money likely
nsw-gateway-review-system::DSSA-G3-7.3.6Costs inside budget and funding affordable
nsw-gateway-review-system::DSSA-G3-7.3.7Cyber protection costs identified
nsw-gateway-review-system::DSSA-G3-7.3.8Realistic view of ability to succeed
nsw-gateway-review-system::DSSA-G3-7.3.9Total project scope clearly defined
nsw-gateway-review-system::DSSA-G3-7.4.1Identification and financial evaluation of major risks
nsw-gateway-review-system::DSSA-G3-7.4.2Risk management plans and allocated ownership
nsw-gateway-review-system::DSSA-G3-7.4.3Resolution of identified issues
nsw-gateway-review-system::DSSA-G3-7.4.4Handling external issues
nsw-gateway-review-system::DSSA-G3-7.4.5Cyber security risk identification and evaluation
nsw-gateway-review-system::DSSA-G3-7.4.6Staff wellbeing and burnout mitigation
nsw-gateway-review-system::DSSA-G3-7.5.1Project control over schedule and cost
nsw-gateway-review-system::DSSA-G3-7.5.2Explanation and reconciliation of deviations
nsw-gateway-review-system::DSSA-G3-7.5.3Actions to prevent repeat deviations
nsw-gateway-review-system::DSSA-G3-7.5.4Verification of Gate 3 assumptions
nsw-gateway-review-system::DSSA-G3-7.5.5Time and tolerance for defect remediation
nsw-gateway-review-system::DSSA-G3-7.5.6Impact of incremental planning on staff and schedule
nsw-gateway-review-system::DSSA-G3-7.5.7Budget control and burn rate
nsw-gateway-review-system::DSSA-G3-7.5.8Consideration of AI use
nsw-gateway-review-system::DSSA-G3-7.5.9AI risk mitigation strategies
nsw-gateway-review-system::DSSA-G3-7.6.1A realistic plan for the stages that remain
nsw-gateway-review-system::DSSA-G3-7.6.2Whether project timescales are reasonable
nsw-gateway-review-system::DSSA-G3-7.6.3Next stage plans, defined and resourced
nsw-gateway-review-system::DSSA-G3-7.6.4Skills and experience available to the team
nsw-gateway-review-system::DSSA-G3-7.6.5Preparing end users for transition
nsw-gateway-review-system::DSSA-G3-7.6.6Legacy system data transfer, integration and exit

Gate 5: Pre-commissioning and readiness for service – NSW Gateway Review System

67 controls
Controls in the Gate 5: Pre-commissioning and readiness for service – NSW Gateway Review System domain of NSW Gateway Review System: 67 controls
CodeTitle
nsw-gateway-review-system::DSSA-G5-3.2Starting and preparing a Gate 5 review
nsw-gateway-review-system::DSSA-G5-3.3.1Mandatory Gate 5 documents
nsw-gateway-review-system::DSSA-G5-3.3.2Supporting information for the review
nsw-gateway-review-system::DSSA-G5-4.1Applying the Gate 5 approach
nsw-gateway-review-system::DSSA-G5-4.2Conducting the Gate 5 review
nsw-gateway-review-system::DSSA-G5-4.7Coverage of Gate 5 review objectives
nsw-gateway-review-system::DSSA-G5-7.2.1Continued need for the project
nsw-gateway-review-system::DSSA-G5-7.2.10Remaining work held to the MVP
nsw-gateway-review-system::DSSA-G5-7.2.11Delegations for decisions and budget
nsw-gateway-review-system::DSSA-G5-7.2.12Operating model resourcing for the MVP
nsw-gateway-review-system::DSSA-G5-7.2.13Authority of business product managers
nsw-gateway-review-system::DSSA-G5-7.2.14Further development and the service portfolio
nsw-gateway-review-system::DSSA-G5-7.2.15Reviewing needs and tracking benefits
nsw-gateway-review-system::DSSA-G5-7.2.2Business need met by the solution
nsw-gateway-review-system::DSSA-G5-7.2.3Validity of the business case
nsw-gateway-review-system::DSSA-G5-7.2.4Post award changes and business change plans
nsw-gateway-review-system::DSSA-G5-7.2.5Agency readiness for business change
nsw-gateway-review-system::DSSA-G5-7.2.6Capacity to deliver and sustain services
nsw-gateway-review-system::DSSA-G5-7.2.7Skilled resources available for delivery
nsw-gateway-review-system::DSSA-G5-7.2.8Movements in benefits and project value
nsw-gateway-review-system::DSSA-G5-7.2.9Strategy for planning and managing benefits
nsw-gateway-review-system::DSSA-G5-7.3.1Risks and issues from contract award
nsw-gateway-review-system::DSSA-G5-7.3.2Implementation risks and issues managed
nsw-gateway-review-system::DSSA-G5-7.3.3Weighing proceed against delay
nsw-gateway-review-system::DSSA-G5-7.3.4Budget control and spending pace
nsw-gateway-review-system::DSSA-G5-7.3.5Consideration of AI use and risks
nsw-gateway-review-system::DSSA-G5-7.3.6Mitigation of AI risks
nsw-gateway-review-system::DSSA-G5-7.4.1Service meets acceptance criteria
nsw-gateway-review-system::DSSA-G5-7.4.10Alignment with government ICT policy
nsw-gateway-review-system::DSSA-G5-7.4.11Alignment with sustainability plan
nsw-gateway-review-system::DSSA-G5-7.4.12E-waste policy for replaced systems
nsw-gateway-review-system::DSSA-G5-7.4.13Non-functional requirements proven by testing
nsw-gateway-review-system::DSSA-G5-7.4.14Progress tracked, reported and corrected
nsw-gateway-review-system::DSSA-G5-7.4.15Legacy data transfer and exit plans
nsw-gateway-review-system::DSSA-G5-7.4.16Incremental planning load on resources
nsw-gateway-review-system::DSSA-G5-7.4.17Contingency for non-digital services
nsw-gateway-review-system::DSSA-G5-7.4.18Effective change management and control
nsw-gateway-review-system::DSSA-G5-7.4.19Cyber security change managed well
nsw-gateway-review-system::DSSA-G5-7.4.2Project control against plan and budget
nsw-gateway-review-system::DSSA-G5-7.4.20Lessons captured from past releases
nsw-gateway-review-system::DSSA-G5-7.4.3Stakeholder issues resolved and reported
nsw-gateway-review-system::DSSA-G5-7.4.4Testing and commissioning completed
nsw-gateway-review-system::DSSA-G5-7.4.5Parties accept commissioning and test results
nsw-gateway-review-system::DSSA-G5-7.4.6Contingency and reversion plans tested
nsw-gateway-review-system::DSSA-G5-7.4.7Parties agree rollout and migration plans
nsw-gateway-review-system::DSSA-G5-7.4.8Contract changes recorded and approved
nsw-gateway-review-system::DSSA-G5-7.4.9Agency ready to manage the contract
nsw-gateway-review-system::DSSA-G5-7.5.1Project elements ready for service
nsw-gateway-review-system::DSSA-G5-7.5.10End users prepared for transition
nsw-gateway-review-system::DSSA-G5-7.5.11Effective move to business as usual
nsw-gateway-review-system::DSSA-G5-7.5.2Ownership after handover understood
nsw-gateway-review-system::DSSA-G5-7.5.3Ready for new ways of working
nsw-gateway-review-system::DSSA-G5-7.5.4Long-term contract management in place
nsw-gateway-review-system::DSSA-G5-7.5.5Benefits managed and measured
nsw-gateway-review-system::DSSA-G5-7.5.6Ongoing operation and maintenance considered
nsw-gateway-review-system::DSSA-G5-7.5.7Post-implementation review process
nsw-gateway-review-system::DSSA-G5-7.5.8Release and transition communications planned
nsw-gateway-review-system::DSSA-G5-7.5.9Time for integration and readiness testing
nsw-gateway-review-system::INSW-G5-INITIATING-THE-REVIEWInitiating the Gateway Review
nsw-gateway-review-system::INSW-G5-KFA1Delivered scope matched to service need
nsw-gateway-review-system::INSW-G5-KFA2Value for money and affordability assurance
nsw-gateway-review-system::INSW-G5-KFA3Readiness for sustainability and network integration
nsw-gateway-review-system::INSW-G5-KFA4Governance through commissioning and handover
nsw-gateway-review-system::INSW-G5-KFA5Risk management for commissioning and operation
nsw-gateway-review-system::INSW-G5-KFA6Stakeholder management for readiness
nsw-gateway-review-system::INSW-G5-KFA7Needs of the asset owner and change management
nsw-gateway-review-system::INSW-G5-MANDATORY-DOCUMENTSRequired information and mandatory documents

Gate 6: Closure review – NSW Gateway Review System

48 controls
Controls in the Gate 6: Closure review – NSW Gateway Review System domain of NSW Gateway Review System: 48 controls
CodeTitle
nsw-gateway-review-system::DSSA-G6-3.2Initiating a Gate 6 review
nsw-gateway-review-system::DSSA-G6-3.3.1Mandatory documents for the review
nsw-gateway-review-system::DSSA-G6-3.3.2Required information on benefits and lessons
nsw-gateway-review-system::DSSA-G6-3.3.3Supporting information for the review
nsw-gateway-review-system::DSSA-G6-3.3.4Alignment project briefing session
nsw-gateway-review-system::DSSA-G6-3.3.5Collaboration on the draft report
nsw-gateway-review-system::DSSA-G6-4.1Gate 6 review approach
nsw-gateway-review-system::DSSA-G6-4.2Conduct of the Gate 6 review
nsw-gateway-review-system::DSSA-G6-7.2.1Service operating within defined parameters
nsw-gateway-review-system::DSSA-G6-7.2.10Whole of government ICT policy alignment
nsw-gateway-review-system::DSSA-G6-7.2.11Ongoing development release and deployment resourced
nsw-gateway-review-system::DSSA-G6-7.2.12Progress toward the target service model
nsw-gateway-review-system::DSSA-G6-7.2.13Checkpoints for ongoing deployment
nsw-gateway-review-system::DSSA-G6-7.2.2Service benchmarked or market tested
nsw-gateway-review-system::DSSA-G6-7.2.3Project documentation delivered and kept current
nsw-gateway-review-system::DSSA-G6-7.2.4Governance and contractual relationships satisfactory
nsw-gateway-review-system::DSSA-G6-7.2.5Continuity in contract management and client knowledge
nsw-gateway-review-system::DSSA-G6-7.2.6Ongoing risk management plans current
nsw-gateway-review-system::DSSA-G6-7.2.7Change management effective
nsw-gateway-review-system::DSSA-G6-7.2.8Relationship management effective
nsw-gateway-review-system::DSSA-G6-7.2.9Training and support adequate
nsw-gateway-review-system::DSSA-G6-7.3.1Business Case still valid
nsw-gateway-review-system::DSSA-G6-7.3.2Benefits realised against expectations
nsw-gateway-review-system::DSSA-G6-7.3.3Business, user and stakeholder needs changed
nsw-gateway-review-system::DSSA-G6-7.3.4Statutory, communications and personnel matters addressed
nsw-gateway-review-system::DSSA-G6-7.3.5Users satisfied with the operational service
nsw-gateway-review-system::DSSA-G6-7.3.6Stakeholder needs review and benefits monitoring
nsw-gateway-review-system::DSSA-G6-7.3.7Business Case reflects next period and lessons
nsw-gateway-review-system::DSSA-G6-7.3.8Stakeholders kept up to date
nsw-gateway-review-system::DSSA-G6-7.4.1Routes to improved value for money
nsw-gateway-review-system::DSSA-G6-7.4.2Contracted processes compared with peers
nsw-gateway-review-system::DSSA-G6-7.4.3Commercial mechanisms provide incentives
nsw-gateway-review-system::DSSA-G6-7.4.4Forward plans affordable
nsw-gateway-review-system::DSSA-G6-7.4.5Asset condition predicted for contract end
nsw-gateway-review-system::DSSA-G6-7.5.1Realistic SMART improvement targets
nsw-gateway-review-system::DSSA-G6-7.5.2Agency and supplier seek innovation
nsw-gateway-review-system::DSSA-G6-7.5.3Planning cycle tracks performance improvement
nsw-gateway-review-system::DSSA-G6-7.5.4Contract measures cover every aspect
nsw-gateway-review-system::DSSA-G6-7.5.5Measures show contract success
nsw-gateway-review-system::DSSA-G6-7.5.6Improvement measures tracked against baseline
nsw-gateway-review-system::DSSA-G6-7.5.7Measures across delivery, change and contract impact
nsw-gateway-review-system::DSSA-G6-7.6.1Process for embedding lessons as they arise
nsw-gateway-review-system::DSSA-G6-7.6.2Project management formally reviewed
nsw-gateway-review-system::DSSA-G6-7.6.3Suppliers urged to learn from experience
nsw-gateway-review-system::DSSA-G6-7.6.4Lessons collected and promoted
nsw-gateway-review-system::DSSA-G6-7.7.1Continued need for the service
nsw-gateway-review-system::DSSA-G6-7.7.2Likely future scope of the service
nsw-gateway-review-system::DSSA-G6-7.7.3Contract issues affecting re-competition

Health Check reviews – NSW Gateway Review System

165 controls
Controls in the Health Check reviews – NSW Gateway Review System domain of NSW Gateway Review System: 165 controls
CodeTitle
nsw-gateway-review-system::DSSA-HC-3.2Register the project and start the review six weeks out
nsw-gateway-review-system::DSSA-HC-3.3How the agency opens the review through governance
nsw-gateway-review-system::DSSA-HC-4.1Assess project against scope and objectives
nsw-gateway-review-system::DSSA-HC-4.2Hold interviews and issue the rated report
nsw-gateway-review-system::DSSA-HC-4.7Record assessment of each review objective
nsw-gateway-review-system::DSSA-HC-7.10.1Project viability maintained
nsw-gateway-review-system::DSSA-HC-7.10.10Super user support after go live
nsw-gateway-review-system::DSSA-HC-7.10.11Development held to the MVP
nsw-gateway-review-system::DSSA-HC-7.10.12Authority for decisions and budget
nsw-gateway-review-system::DSSA-HC-7.10.13Operating model resourced for the MVP
nsw-gateway-review-system::DSSA-HC-7.10.14Business users able to drive change
nsw-gateway-review-system::DSSA-HC-7.10.15Continual development and portfolio growth
nsw-gateway-review-system::DSSA-HC-7.10.16Benefits reviewed and tracked
nsw-gateway-review-system::DSSA-HC-7.10.17Time for integration and readiness testing
nsw-gateway-review-system::DSSA-HC-7.10.18End users prepared for transition
nsw-gateway-review-system::DSSA-HC-7.10.2Business need still met
nsw-gateway-review-system::DSSA-HC-7.10.3Business case remains valid
nsw-gateway-review-system::DSSA-HC-7.10.4Changes between award and transition
nsw-gateway-review-system::DSSA-HC-7.10.5Ready for business change
nsw-gateway-review-system::DSSA-HC-7.10.6Implement while keeping services running
nsw-gateway-review-system::DSSA-HC-7.10.7Team skills and experience
nsw-gateway-review-system::DSSA-HC-7.10.8Benefit changes affecting project value
nsw-gateway-review-system::DSSA-HC-7.10.9Strategy for planning and managing benefits
nsw-gateway-review-system::DSSA-HC-7.11.1Service meets acceptance criteria
nsw-gateway-review-system::DSSA-HC-7.11.10Alignment with the sustainability plan
nsw-gateway-review-system::DSSA-HC-7.11.11E waste policy considered
nsw-gateway-review-system::DSSA-HC-7.11.12Whole of government ICT compliance
nsw-gateway-review-system::DSSA-HC-7.11.13Non functional requirements tested
nsw-gateway-review-system::DSSA-HC-7.11.14Progress tracked, reported and corrected
nsw-gateway-review-system::DSSA-HC-7.11.15Legacy data transfer and exit
nsw-gateway-review-system::DSSA-HC-7.11.16Incremental planning load
nsw-gateway-review-system::DSSA-HC-7.11.17Contingency for non digital users
nsw-gateway-review-system::DSSA-HC-7.11.18Change managed and controlled
nsw-gateway-review-system::DSSA-HC-7.11.19Lessons from past releases
nsw-gateway-review-system::DSSA-HC-7.11.2Running to plan and budget
nsw-gateway-review-system::DSSA-HC-7.11.20Communications for releases and go live
nsw-gateway-review-system::DSSA-HC-7.11.21When releases cease
nsw-gateway-review-system::DSSA-HC-7.11.3Stakeholder issues addressed
nsw-gateway-review-system::DSSA-HC-7.11.4Testing and commissioning completed
nsw-gateway-review-system::DSSA-HC-7.11.5Parties accept commissioning results
nsw-gateway-review-system::DSSA-HC-7.11.6Contingency, continuity and rollback plans
nsw-gateway-review-system::DSSA-HC-7.11.7Parties agree change and migration plans
nsw-gateway-review-system::DSSA-HC-7.11.8Contract changes recorded and approved
nsw-gateway-review-system::DSSA-HC-7.11.9Ready to manage the contract operationally
nsw-gateway-review-system::DSSA-HC-7.12.1Award phase risks resolved
nsw-gateway-review-system::DSSA-HC-7.12.2Implementation risks identified and managed
nsw-gateway-review-system::DSSA-HC-7.12.3Risk of proceeding versus delaying
nsw-gateway-review-system::DSSA-HC-7.12.4Budget control and burn rate
nsw-gateway-review-system::DSSA-HC-7.2.1Business need and strategic fit
nsw-gateway-review-system::DSSA-HC-7.2.10Stakeholder support and agency commitment
nsw-gateway-review-system::DSSA-HC-7.2.11Benefits agreed and realisation planned
nsw-gateway-review-system::DSSA-HC-7.2.12Change plan developed with business units
nsw-gateway-review-system::DSSA-HC-7.2.13Changes across business areas managed
nsw-gateway-review-system::DSSA-HC-7.2.14Benefit changes and management strategy
nsw-gateway-review-system::DSSA-HC-7.2.15Capability and capacity assessed
nsw-gateway-review-system::DSSA-HC-7.2.16Cyber work reflected in delivery strategy
nsw-gateway-review-system::DSSA-HC-7.2.17Resources to sustain momentum
nsw-gateway-review-system::DSSA-HC-7.2.18Emerging benefits fed into the case
nsw-gateway-review-system::DSSA-HC-7.2.19Roles, responsibilities and delegations
nsw-gateway-review-system::DSSA-HC-7.2.2Preferred option still appropriate
nsw-gateway-review-system::DSSA-HC-7.2.20Training for service and front-line staff
nsw-gateway-review-system::DSSA-HC-7.2.21Business change management processes
nsw-gateway-review-system::DSSA-HC-7.2.22Business users empowered to drive change
nsw-gateway-review-system::DSSA-HC-7.2.23Progress tracked, reported and corrected
nsw-gateway-review-system::DSSA-HC-7.2.3Whole-life value for money
nsw-gateway-review-system::DSSA-HC-7.2.4Costs within budget and funding affordable
nsw-gateway-review-system::DSSA-HC-7.2.5Realistic view of ability to succeed
nsw-gateway-review-system::DSSA-HC-7.2.6Total project scope defined
nsw-gateway-review-system::DSSA-HC-7.2.7Security requirements identified early
nsw-gateway-review-system::DSSA-HC-7.2.8Cyber protection costs included
nsw-gateway-review-system::DSSA-HC-7.2.9Business change risks in an initial plan
nsw-gateway-review-system::DSSA-HC-7.3.1Project under control
nsw-gateway-review-system::DSSA-HC-7.3.2Causes of budget and schedule deviation
nsw-gateway-review-system::DSSA-HC-7.3.3Actions to prevent repeat deviation
nsw-gateway-review-system::DSSA-HC-7.3.4Assumptions from Gate 2 verified
nsw-gateway-review-system::DSSA-HC-7.3.5Time to fix faults and manage slippage
nsw-gateway-review-system::DSSA-HC-7.3.6Incremental planning load on team
nsw-gateway-review-system::DSSA-HC-7.3.7Budget control and spend rate
nsw-gateway-review-system::DSSA-HC-7.4.1Options tested against needs and priorities
nsw-gateway-review-system::DSSA-HC-7.4.10Knowledge of the supplier market
nsw-gateway-review-system::DSSA-HC-7.4.11Robust contract management strategy
nsw-gateway-review-system::DSSA-HC-7.4.12Evaluation strategy accepted and compliant
nsw-gateway-review-system::DSSA-HC-7.4.13Whole-of-government ICT policy alignment
nsw-gateway-review-system::DSSA-HC-7.4.2Shared understanding of business needs
nsw-gateway-review-system::DSSA-HC-7.4.3Requirements specification matches outcomes
nsw-gateway-review-system::DSSA-HC-7.4.4Sourcing options evaluated
nsw-gateway-review-system::DSSA-HC-7.4.5Market appetite for the requirement
nsw-gateway-review-system::DSSA-HC-7.4.6Procurement approach and state rules
nsw-gateway-review-system::DSSA-HC-7.4.7Defined delivery strategy
nsw-gateway-review-system::DSSA-HC-7.4.8Delivery strategy influences addressed
nsw-gateway-review-system::DSSA-HC-7.4.9The strategy supports communication and joint working
nsw-gateway-review-system::DSSA-HC-7.5.1Risks identified and financially evaluated
nsw-gateway-review-system::DSSA-HC-7.5.2Risk management plans in place
nsw-gateway-review-system::DSSA-HC-7.5.3Issues satisfactorily resolved
nsw-gateway-review-system::DSSA-HC-7.5.4External issues and plans for stakeholders
nsw-gateway-review-system::DSSA-HC-7.5.5Staff exhaustion risk and mitigation
nsw-gateway-review-system::DSSA-HC-7.6.1Project still required
nsw-gateway-review-system::DSSA-HC-7.6.10Change management with business units
nsw-gateway-review-system::DSSA-HC-7.6.11Changes across business areas managed
nsw-gateway-review-system::DSSA-HC-7.6.12Benefit changes and project value
nsw-gateway-review-system::DSSA-HC-7.6.13Strategy for planning benefits
nsw-gateway-review-system::DSSA-HC-7.6.14Supplier delivery capability verified
nsw-gateway-review-system::DSSA-HC-7.6.15Supplier timeline and variation impacts
nsw-gateway-review-system::DSSA-HC-7.6.16Remaining build limited to MVP
nsw-gateway-review-system::DSSA-HC-7.6.17Decision and budget delegations defined
nsw-gateway-review-system::DSSA-HC-7.6.18Live operating model supports MVP
nsw-gateway-review-system::DSSA-HC-7.6.19Business users empowered
nsw-gateway-review-system::DSSA-HC-7.6.2Business case completeness
nsw-gateway-review-system::DSSA-HC-7.6.20Service growth and digital portfolio
nsw-gateway-review-system::DSSA-HC-7.6.21Benefits tracked and reviewed
nsw-gateway-review-system::DSSA-HC-7.6.22Integration and readiness testing allowance
nsw-gateway-review-system::DSSA-HC-7.6.23End users prepared for transition
nsw-gateway-review-system::DSSA-HC-7.6.3Preferred option meets the need
nsw-gateway-review-system::DSSA-HC-7.6.4Most appropriate option chosen
nsw-gateway-review-system::DSSA-HC-7.6.5Commercial deal offers whole-life value
nsw-gateway-review-system::DSSA-HC-7.6.6Realistic about managing change
nsw-gateway-review-system::DSSA-HC-7.6.7Full case remains affordable
nsw-gateway-review-system::DSSA-HC-7.6.8Agreed benefits realisation plan
nsw-gateway-review-system::DSSA-HC-7.6.9Stakeholder involvement and approvals
nsw-gateway-review-system::DSSA-HC-7.7.1Project under control
nsw-gateway-review-system::DSSA-HC-7.7.10E-waste policy for replaced systems
nsw-gateway-review-system::DSSA-HC-7.7.11Whole-of-government ICT alignment
nsw-gateway-review-system::DSSA-HC-7.7.12Non-functional requirements testable
nsw-gateway-review-system::DSSA-HC-7.7.13Progress tracked and corrected
nsw-gateway-review-system::DSSA-HC-7.7.14Legacy systems and data transfer plans
nsw-gateway-review-system::DSSA-HC-7.7.15Incremental planning within capacity
nsw-gateway-review-system::DSSA-HC-7.7.16Contingency for non-digital users
nsw-gateway-review-system::DSSA-HC-7.7.17Change managed effectively
nsw-gateway-review-system::DSSA-HC-7.7.18Lessons from earlier releases
nsw-gateway-review-system::DSSA-HC-7.7.19Release and transition communications
nsw-gateway-review-system::DSSA-HC-7.7.2Causes of deviation explained
nsw-gateway-review-system::DSSA-HC-7.7.20End of release activity and handover
nsw-gateway-review-system::DSSA-HC-7.7.3Actions to stop repeat deviation
nsw-gateway-review-system::DSSA-HC-7.7.4Earlier assumptions validated
nsw-gateway-review-system::DSSA-HC-7.7.5Procurement and technical checks completed
nsw-gateway-review-system::DSSA-HC-7.7.6Delivery strategy followed
nsw-gateway-review-system::DSSA-HC-7.7.7Documents quality reviewed
nsw-gateway-review-system::DSSA-HC-7.7.8Probity issues managed
nsw-gateway-review-system::DSSA-HC-7.7.9Alignment with sustainability plan
nsw-gateway-review-system::DSSA-HC-7.8.1Solution meets the business need
nsw-gateway-review-system::DSSA-HC-7.8.10Technical implications assessed
nsw-gateway-review-system::DSSA-HC-7.8.11Team skills and experience
nsw-gateway-review-system::DSSA-HC-7.8.2Alternative supplier options assessed
nsw-gateway-review-system::DSSA-HC-7.8.3Solution delivers the full case need
nsw-gateway-review-system::DSSA-HC-7.8.4Business change strategy updated
nsw-gateway-review-system::DSSA-HC-7.8.5Benefits and budgets updated
nsw-gateway-review-system::DSSA-HC-7.8.6Ready for build and transition
nsw-gateway-review-system::DSSA-HC-7.8.7Change strategy agreed by all
nsw-gateway-review-system::DSSA-HC-7.8.8Responsibilities and liabilities allocated
nsw-gateway-review-system::DSSA-HC-7.8.9Resources for supplier obligations
nsw-gateway-review-system::DSSA-HC-7.9.1Risk and issue plans current
nsw-gateway-review-system::DSSA-HC-7.9.2Major phase risks resolved
nsw-gateway-review-system::DSSA-HC-7.9.3Continuity and contingency arrangements
nsw-gateway-review-system::DSSA-HC-7.9.4Contract terms and risk allocation
nsw-gateway-review-system::DSSA-HC-7.9.5Re-competition for long contracts
nsw-gateway-review-system::DSSA-HC-7.9.6Budget controlled and burn rate
nsw-gateway-review-system::INSW-HC-INITIATING-THE-REVIEWStarting the Health Check review
nsw-gateway-review-system::INSW-HC-KFA1Delivery scope aligned to service need
nsw-gateway-review-system::INSW-HC-KFA2Affordability and value for money
nsw-gateway-review-system::INSW-HC-KFA3Social, environmental and economic sustainability
nsw-gateway-review-system::INSW-HC-KFA4Accountabilities and governance structure
nsw-gateway-review-system::INSW-HC-KFA5Live risk management and mitigation
nsw-gateway-review-system::INSW-HC-KFA6Interfaces and stakeholder management
nsw-gateway-review-system::INSW-HC-KFA7Change management and asset owner needs
nsw-gateway-review-system::INSW-HC-MANDATORY-DOCUMENTSRequired information and mandatory documents

Preparing for and conducting a gateway review (all gates) – NSW Gateway Review System

7 controls
Controls in the Preparing for and conducting a gateway review (all gates) – NSW Gateway Review System domain of NSW Gateway Review System: 7 controls
CodeTitle
nsw-gateway-review-system::REV-3.3.3Preplanning planning session
nsw-gateway-review-system::REV-3.3.4Review activities and interview week
nsw-gateway-review-system::REV-3.3.5Draft and final review report
nsw-gateway-review-system::REV-4.3Reviewer team skills and independence
nsw-gateway-review-system::REV-4.4Review principles and behaviours
nsw-gateway-review-system::REV-4.5Review communication protocols
nsw-gateway-review-system::REV-4.6Gateway review report quality

Rapid Assurance Review – NSW Gateway Review System

9 controls
Controls in the Rapid Assurance Review – NSW Gateway Review System domain of NSW Gateway Review System: 9 controls
CodeTitle
nsw-gateway-review-system::DSSA-RAR-3.2Start the review with the GCA
nsw-gateway-review-system::DSSA-RAR-3.3Agency authorisation and existing documents
nsw-gateway-review-system::DSSA-RAR-3.3.1Mandatory project documents for the review
nsw-gateway-review-system::DSSA-RAR-3.3.2Confirm required information for the review
nsw-gateway-review-system::DSSA-RAR-3.3.3Hold the project alignment briefing
nsw-gateway-review-system::DSSA-RAR-3.3.4Agency presentation and working with the reviewer
nsw-gateway-review-system::DSSA-RAR-3.3.5How the review report is drafted and finalised
nsw-gateway-review-system::DSSA-RAR-4.1Review approach against scope and objectives
nsw-gateway-review-system::DSSA-RAR-4.2How the Rapid Assurance Review is conducted

What is NSW Gateway Review System and who does it apply to?

NSW Gateway Review System is a compliance framework from Australia (New South Wales) with 8 domains and 449 controls. The NSW Government's gateway review system: what delivery agencies are expected to show and review teams probe at Gate 0, Gate 2, Gate 3, Gate 5, Gate 6, the Health Checks and the Rapid Assurance Review for digital projects, with the Infrastructure NSW key focus areas at Gate 0, Gate 5 and the delivery Health Check, and the steps for initiating and conducting a review. It is used by organisations to establish and maintain compliance with industry standards and regulatory requirements.

What does NSW Gateway Review System actually require?

NSW Gateway Review System has 449 controls organised across 8 domains. The largest domains are Health Check reviews – NSW Gateway Review System (165 controls), Gate 3: Pre-execution – NSW Gateway Review System (70 controls), Gate 5: Pre-commissioning and readiness for service – NSW Gateway Review System (67 controls). Each control defines specific requirements that organisations must implement to achieve compliance.

If I already comply with another framework, how much of NSW Gateway Review System do I already cover?

NSW Gateway Review System does not currently have cross-framework mappings in our system. Check back as we continuously expand our mapping database.

How do I implement NSW Gateway Review System?

Start your NSW Gateway Review System compliance journey by running a self-assessment on our platform to identify your current compliance posture. Our AI advisory can answer specific questions about NSW Gateway Review System requirements, and cross-framework mapping helps you leverage existing controls from other frameworks you may already comply with. Create a free account to access all 449 controls and track your progress.