ISO 21502:2020 7.6: Schedule management

What does 7.6 require?

The schedule should sit inside the project plan and should be built under the project manager's direction by putting activities in order, estimating how long each takes, and creating and controlling the schedule with the people who do the work or are affected by it. Activities should be ordered logically with dependencies so the critical path can be identified or alternatives found. Progress should be tracked against the approved baseline so the scope is delivered on time, with the state of each phase, work package and activity monitored, changes managed, milestones watched and other controls added as needed, using methods such as earned value where they fit. Before the schedule is built, the project manager and team should estimate the duration of each activity, planning near-term work in more detail and later work in less, balancing schedule constraints against resource availability and re-estimating at intervals to refresh forecasts against the baseline. Once activities are baselined, revisions should go through change requests, and new risks and other effects on the project should be identified at the same time. Activities should be scheduled to suit the delivery approach in enough detail to assign work and resources, finalise the budget and keep management control, using a network diagram or other formats. The schedule should show whether objectives can be met on time, where the critical path lies and what risks sit on it, and how actual progress compares with a predefined baseline. Building and reviewing the schedule should continue through the project as plans change and risks emerge, with duration and resource estimates revised where needed so an approved baseline supports tracking. Once the schedule and baseline are approved, control should track the work, spot variance and take preventive or corrective action as needed. The project manager should watch for the effect of early delays and weigh trade-offs such as risk against cost when responding, realigning to the original baseline or setting a new one with the least possible impact, and treating early completion as an opportunity. Control should establish progress to date, compare it with the approved baseline, forecast completion dates and act to prevent adverse delay, with completion forecasts refreshed routinely from trends and current knowledge and acceleration using reserves or other strategies where possible.

Maintained by Gerard Blokdyk

Other controls in Clause 7: Management practices for a project – ISO 21502:2020

Query this from an agent

The graph holds this control, the 0 it maps to, and the evidence behind each claim, over MCP and REST.