A PCBU proposing demolition of a structure or loadbearing part of a structure at least 6 metres high (measured from the lowest adjacent ground to the highest point), demolition involving load shifting machinery on a suspended floor, or demolition involving explosives gives the regulator written notice in the required manner and form at least 5 days before the work starts; an emergency service organisation gives notice as soon as practicable, before or after.